2016-2017 FACILITIES CAPITAL IMPROVEMENTS PROJECTS:

In Design

1.     Austin Elementary:

§  Gym Addition/Improvements

2.      Secured Entrances Phase III:

§  13 Locations

 

3.      ENHS:

§  Paving Improvements

4.     Hargill Elementary: Negrete Architect

§  Gym/Classroom Addition

5.      Memorial Eisenhower Sports Complex: SDI Engineer - Millennium

§  Park - Bids September 2016

 

6.      JEHS: District Architect

§  Perimeter Sidewalk 

7.     Travis Elementary: District Architect

§  Student Drop-off Canopy/Parking Lot Lighting

8.      LBJ, San Carlos, Austin, Trevino, JFK: District Architect

§  Playscapes

 



Bidding

1.      Avila Elementary: ROFA Architect t- RABA

§  Classroom Addition - Bids 9/15/16

 

2.      EHS,ENHS,JEHS: ERO Architect - RABA

§  PAC A/V & Ticket Booth - Facilities Update 9/16/16


Construction

1.      RVHS: SDI Engineer - Millennium

§  Paving/Draining Improvements - IOC Construction 90%

Scheduled to Complete 9/26/16

 

2.      Transportation Shop: Rio Delta Engineer - RABA

§  Paving/Drainage Improvements - Texas Cordia 90%

Scheduled to Complete 9/15/16

 

3.      Transportation, District Police, EHS : District Architect - RABA

§  Lounge, Kennel Security Hut - JCON Construction 85%

Scheduled to Complete 9/15/16

 

4.      EHS: Dannenbaum Engineering - RABA

§  Site Draining Improvements - NM Contracting 95%

Metal Roof Installed 8/29/16

 

5.      BL Garza: PBK Architects - Millennium

§  Athletics Addition - Candela Construction - 25%

Substantial Completion January 2017

 

6.      ENHS: Amtech Architect

§  Gym/Cafeteria Roof - Rio Roofing

Substantial Completion December 2016

 

7.      Richard R. Flores Stadium: SDI Engineer

§  Fencing/Light & Building Plaque/Letters - G&G Construction 55%

Plaque and Letter Installed by  9/6/16

 

8.      District Middle Schools: Melden & Hunt Engineer

§  Softball Fields Irrigation - Green Thumb


9.      ECISD/County of Hidalgo Precinct 4:

§  Brewster Park - Construction 0%


10.      ECISD/County of Hidalgo Drainage District #1:

§  San Carlos Kennedy Drainage Ditch - Construction 95%

Scheduled to Complete 9/15/16

 

11.      ECISD/Edinburg City/McAllen City/ County Precinct 4/Drainage District #1:

§  Mile 171/2 Road Paving - Construction 95%

Scheduled to Complete 9/15/16